News & media.

Every filing, permit step, town vote, and broadcast since the joint venture was signed in January. Nothing here is our summary of a summary — each entry links to the original.

Where it stands today

Town moratorium
days left — expires Aug 28

Adopted unanimously June 29 on construction in the Industrial Heavy District. Residents had asked for six months.

Air permit
No draft
permit published yet

DEQ is still evaluating the application for technical adequacy. The formal public comment window opens only when a draft permit is issued.

State lawsuit
Venue
contested — removal filed Jul 21

The Attorney General sued in Rogers County. The companies want the case heard in federal court in Tulsa instead.

Company schedule
Q1 2027
target construction start

Bankable feasibility study due September. The companies say they want every permit in hand by the end of this year.

On camera

Watch the meetings.

Local broadcast coverage and the Attorney General's full press conference, in the order they happened.

Jun 2, 2026Press conference

Attorney General Drummond’s full remarks

The complete announcement of the petition to block the smelter, delivered to applause from the residents who gathered for it.

Jun 3, 2026Broadcast report

Drummond files to block the project

The filing in Rogers County District Court and the statewide fight it set off between the Attorney General, the governor, and the White House.

Feb 28, 2026Broadcast report

Support and opposition both harden

Supporters say the project reshapes Oklahoma’s economy. Neighbors say it does not belong on the other side of their fence line.

Mar 2026Broadcast report

Inside the company open house

Residents question Oklahoma Primary Aluminum staff directly — the first time most of them could ask anyone anything.

Feb 7, 2026Broadcast report

Residents raise health and environment concerns

The earliest sustained local coverage of what neighbors were already asking about hydrogen fluoride, months before the permit landed.

The record

Six months, 15 entries.

Jul 21, 2026
LegalOklahoma Energy Today

Century Aluminum and Aluminum Oklahoma file a Notice of Removal, seeking to move the Attorney General’s suit out of Rogers County and into federal court in Tulsa.

Jul 18, 2026
ProjectSouthwest Ledger

Project director Ziad Fares says a bankable feasibility study is due in September, all permits by year end, and construction by the end of the first quarter of 2027.

Jul 6, 2026
PoliticsOklahoma Voice

In a county that voted overwhelmingly for the president, residents publicly reject his deal to build a foreign-owned smelter beside their homes.

Jul 1, 2026
LegalKOSU

Tulsa Ports warns the town that interfering with the port’s purpose “will necessitate a response.” Oklahoma Primary Aluminum says it would have an obligation to pursue legal remedies to recover its investment losses.

Jun 29, 2026
LocalNews on 6

After more than five hours of comment and a closed executive session, councilors unanimously adopt a 60-day moratorium on construction in the Industrial Heavy District — not the six months residents came to ask for.

Jun 29, 2026
LocalKOSU

A letter from the president urging approval “without delay” is read to the room. An attendee answers: build it in Mar-a-Lago.

Jun 10, 2026
LocalOklahoma Watch

The project’s quiet supporters run the school district and the career tech center. The superintendent describes lifelong friendships severed over a plant that does not exist yet.

Jun 10, 2026
PoliticsCanary Media

The smelter is swept into the governor’s race. Drummond denies political motive and points to the air-quality permit application as the reason for his filing.

Jun 8, 2026
LocalNews on 6

A standing-room-only council declines to pass the six-month moratorium as written and tables it for redrafting. It does approve ICARE, a resident committee with a formal voice in planning decisions.

Jun 2, 2026
LegalOffice of the Attorney General

Drummond petitions Rogers County District Court for a permanent injunction halting all construction. The suit seeks no damages — only that the project not be built.

Apr 24, 2026
Permits2 News Oklahoma

DEQ tells a packed room the permit application is still being evaluated for technical adequacy. Doubts persist; the opposition petition passes 2,000 signatures.

Apr 13, 2026
ScrutinyOklahoma Watch

An energy expert examines the smelter’s power appetite and finds unanswered questions that could reshape the region’s farms, livestock, and public health.

Apr 9, 2026
ScrutinyThe Frontier

One of the two companies behind the project has a documented history of air pollution violations at its existing American plants.

Feb 9, 2026
ProjectGlobeNewswire

Bechtel is hired for preparatory engineering, with the stated goal of a final investment decision and construction start by the end of 2026.

Jan 26, 2026
ProjectNewsfile

EGA and Century Aluminum sign the joint development agreement — 60 percent Emirati, 40 percent American — for a plant sized at 750,000 tonnes a year, larger than first announced.

Community archive

Photographs and drone footage from Inola residents.

Aerial — port site

Port of Inola — the 440-acre site

Hay field / pasture

Hay ground inside the fluoride zone

Town hall crowd

June 29 — standing room only

Cattle

Herds downwind of the stacks

Yard signs / shirts

Teal shirts, hand-made signs

Verdigris River

The Verdigris, at the barge terminal

Primary sources

Read it yourself.

The state publishes the permit file. The Attorney General published his petition. Nothing on this site asks you to take our word for it.

Air quality construction permit file
Oklahoma DEQ — official project page
Petition to block the smelting complex
Office of the Attorney General — June 2, 2026

The moratorium is counting down.

Sixty days was what the town could get. What happens next depends on how many people are still paying attention when the clock runs out.